For Sub-Station
- Only dry-type of transformers shall be used for installations inside the residential & commercial buildings.
- Oil filled transformers installed indoors other than in residential or commercial buildings are to be placed at the ground floor or not below the first basement.
- Duly filled and signed Form of Inspection Report
- Single line diagram of the installation showing supply & load side;
- Front & Plan view and equipment layout diagrams with dimensions and clearance from nearby structures/ buildings;
- A sketch showing earthing system;
- Original copy of Treasury Challan towards applicable Inspection Fee.
- In case of consumers installation, the following additional documents are to be furnished:
- Copy of load sanction letter;
- Permission/NOC for building installation & approved drawing;
- No Objection or permission from land/premises owner;
- Manufacturer’s test certificate of the Transformer, Circuit Breaker & other prime equipment;
- Detailed load schedule and test report;
- Electrical layout drawings;
- Copy of Provisional Estimate;
- Contractor, Supervisor, and Workman certificates;
For Multi-storied High Rise Building (Height > 15 meters)
- Duly filled and signed Form of Inspection Report
- Electrical layout drawings including earthing & Lightening arrestor;
- Details load schedule and test report;
- Permission/NOC for construction and approved drawings;
- Original copy of Treasury Challan towards Inspection Fee.
- Contractor, Supervisor, and Workman certificates;
For Overhead Line (11 KV/33 KV/132 KV and above)
- Duly filled and signed Form of Inspection Report
- Details of earthing;
- Sketch showing different supports used;
- Sketch of guards with dimensions & clearances;
- Route map and approval under Section 68 of Electricity Act 2003;
- No Objection or permission from land owner;
- Provisional Estimate and PTCC clearance;
- Contractor, Supervisor, and Workman certificates;
For Cable
- Duly filled and signed Form of Inspection Report
- Route map and cable laying system sketch;
- Manufacturer’s test certificate of the cable;
- Original copy of Treasury Challan towards Inspection Fee;
- Contractor, Supervisor, and Workman certificates;
For Generating Set
- Duly filled and signed Form of Inspection Report
- No Objection or permission from land owner;
- Electrical layout drawings with earthing plan;
- Manufacturer’s test certificate of Diesel Generating Set;
- Structural fitness certificate & NOC from Fire Service;
- Purchase document of Generating set;
- Original copy of Treasury Challan towards Inspection Fee;
- Contractor, Supervisor, and Workman certificates;
For Building Plan Approval
- Application via SWAAGAT portal for commercial/industrial buildings;
- Structural layout with safe clearances from Municipal/Development Authority;
- Mutation/Porcha and Tax clearance certificate;
- Original copy of Treasury Challan towards Inspection Fee;
For Polyclinic / Nursing Home/ Private Hospital/Laboratory
- Duly filled and signed Form of Inspection Report
- Mutation/Porcha of the land;
- Tax clearance certificate;
- Rent Agreement (if applicable);
- Single Line Diagram of electrical wiring;
- Trade License, Aadhar & PAN card of applicant;
- Original copy of Treasury Challan towards Inspection Fee;
- Contractor, Supervisor, and Workman certificates;
For Drawing Approval
- Application format for submission of drawings;
- Completion Certificate of electrical installation;
- Structural layout and safe clearances;
- Mutation/Porcha and Tax clearance certificate;
- Single Line Diagram of electrical wiring;
- Original copy of Treasury Challan towards Inspection Fee;
- Contractor, Supervisor, and Workman certificates;